Proposed Project Timeline
May 2022 | BOE approved the “Renovate-as-New” option to move forward to the Town Council |
---|---|
June 2022 | MSP "Renovate as New" Project & Cost Estimate Introduced to the Town Council |
December 2023 | Town Council introduced proposed Ordinance setting course for the "Renovate as New" project and projected Referendum |
February 5, 2024 | Public Hearing on the Ordinance to set Referendum at Regular Town Council Meeting |
February 13, 2024 | Special Town Council Meeting to set Referendum |
March 19, 2024 | Projected Referendum |
June 2024 | Reimbursement application submitted to the State of Connecticut for review and approval |
Mid 2024 - Mid 2025 | State reviews application and issues approval |
Mid - Late 2025 | Owners Project Manager, Architect & Engineer, and Construction Manager Selected |
2025 | Design Phase Planning and Preconstruction |
Late 2025 - Early 2026 | Bidding |
2026-2028 | Construction (Phases 1 - 3) |
Fall 2028 | Anticipated Project Completion |