Town Line Road Reconstruction Notice

Beginning on or about September 13, 2021, the reconstruction of Town Line Road will begin.  Construction activities have been divided into two phases. 

Phase 1:  South Washington Street to Red Stone Street (Southington)
The first phase will take through the fall of 2021 with an expected substantial completion date of December 2021. 

Phase 2:  Red Stone Hill to 100’ North of Red Stone Street (Southington)
The second phase will begin in April 2022 with an expected substantial completion date of June 2022.  The 100’ gap between the two phases will be reconstructed by CT DOT as part of the multi-use path project in the next several years.

The Town of Plainville has retained Tobacco & Sons Builders of Bristol to reconstruct Town Line Road. Construction activities will involve drainage upgrades, excavation and replacement of the existing roadway base material, repaving and other associated improvements.

Project specific travel delays can be expected on Town Line Road and Red Stone Hill.  Alternating one-way traffic within the work zone will be implemented while certain construction activities proceed.  Thru traffic is urged to seek alternative routes.   Access to businesses along Town Line Road will be maintained during construction.